Christ the King Montessori School
Scope & Services
Endeavor North Design PLLC provided architectural pre-design, code analysis, and construction/permit document services for the renovation of (6) restrooms and (1) laundry room.
Endeavor North Design Build LLC provided general contracting, project and construction management services along with permitting, bidding, and procurement assistance.
The project(s) required a well-coordinated effort as the work was completed from May to August, while school was out of session for the summer. Careful planning and consistent communication with the owners, trade partners, and vendors/suppliers was critical to the success of the project.
Portions of the school are over 80 years old so many of the existing concrete block walls, plumbing, and electrical required updates. Including new doors being added into the concrete block walls.
Schedule management and communication were important in order to deliver the project on an accelerated schedule. Weekly meetings with the trade teams were held and ongoing communication kept the project moving with no downtime. Everyone knew well in advance on when they needed to be on-site for their specific work. Having a jobsite culture of respect and communication created an environment where all parties were aiming for the same end goal.
"Endeavor North Design Build truly heard our calling and took the time to understand our needs. Their team kept the project well-organized, provided consistent weekly updates, and successfully completed multiple restroom renovation projects over the summer break without disruption. Just as importantly, they made the entire process enjoyable along the way."
- Derrick Nagel, Principal
Location
Mandan, ND
Type
Education & Religious
Size
~1000 sf
Completion
2025